Home News Vietnam Car is prohibited from running through Mai Dich – South Thang Long...

Car is prohibited from running through Mai Dich – South Thang Long viaduct

0
0

Construction unit will block the entrance to Mai Dich – Nam Thang Long viaduct from the evening of April 23 to connect 2 ram near Co Nhue intersection.
Exchange with Zing , Representative of Thang Long Project Management Board, investor of Mai Dich – Nam Thang Long viaduct project, said that this viaduct would be temporarily closed from 9pm on 23/4 to 25/4 for the contractor to pour concrete. 2 up and down slopes in Co Nhue area.

“We will finish pouring concrete tonight. However, it is necessary to wait 3 days for the concrete to freeze, to avoid the situation where the vehicle will shake, possibly cracking the bridge deck,” said PMU representative Thang Long. prefer. Nam Thang Long viaduct route will be opened to traffic when the up and down slope is not completed. Photo: Ngoc Tan. This position said the viaduct has 6 slopes up and down, but only the slope in Co Nhue needs to prohibit the road for construction. The remaining 4 ramps are connected to independent box girders, separated from the main bridge, so no road is prohibited. The plan to prohibit roads for construction of up and down slopes has been approved by the Department of Transport of Hanoi. From the evening of April 23, the traffic police and the traffic bar will coordinate with the contractor to divide the traffic flow. Previously, the Mai Dich – South Thang Long viaduct lacked the downhill after the traffic opened, causing many drivers to complain, indirectly leading to the situation where a series of vehicles turned against the rules on the Thang Long bridge. Exchange with Zing Mr. Duong Viet Roan, Director of Thang Long Project Management Board, explained that 6 up and down slopes cannot be constructed at the same time with viaducts due to lack of space. Mr. Roan said the construction unit is speeding up to complete all 6 ramps up and down.